The procedure below defines the steps to be undertaken in carrying out the procurement system thru public bidding for goods and services required by the Bureau of Local Government Finance
Availability of Service: Monday to Friday from 8:00AM to 5:00 PM except on holidays.
Clientele : Service Providers, Contractors, Bidders
How to Avail of the Service:
STEP |
Customer / Client | Service Provider (Offices / Units of BLGF) |
Duration
|
Division / Person In-Charge | Fees | Form / Document |
1 | Prepare Bidding Documents Provides a concise specification or description of the item and the quantityNote:
|
1 week | BAC Secretariat | As specified (Amount may vary) | The bidding documents shall include the following:
|
|
2 | Invitation to Bid
– Newspaper – G-EPS Posting – Bureau’s Website |
3 hrs2 weeks | Bids and Awards Committee BAC Secretariat |
|||
3 | Submits BID Documents and relative requirements to the Bureau’s Records Unit | 10 minutes | Bidder/s | BID Documents and relative requirements | ||
4 | Records Incoming Documents | 10 minutes | Records Officer | None | Logbook | |
5 | Routes Documents to BAC Secretariat | 20 minutes | Records Officer | None | Logbook | |
6 | Receives the BID Documents and affix initials / signature in the logbook | 5minutes | BAC Secretariat | None | Logbook / BID Documents | |
7 | Pre-bid ConferenceNote:
|
4 hrs | Bids and Awards Committee | Bid Documents | ||
8 | Receipt and Opening of Bids
|
4 hrs | Bids and Awards Committee, Technical Working Group and Bidders | Bid Documents | ||
9 | Bid Evaluation
|
3 hrs3 days
|
Bids and Awards Committee,Technical Working Group and BAC Secretariat | Abstract of Bids, Bid Evaluation Report | ||
10 | Award
|
1 week1 day
1day |
Technical Working Group and BAC SecretariatHead of Agency
Bids and Awards Committee Bidder
|
Resolution of BAC to Award, Notice of AwardPerformance Security | ||
11 | Implementation of Contract
|
1 day | Bids and Awards Committee and Winning Bidder | Notice to Proceed, Contract | ||
12 | Delivery , Inspection and Acceptance
For Goods
|
As specified in the contract1 day | Winning BidderCommission on Audit
|
GoodsInspection and Acceptance Report
|
||